End of week 44

Continued progress with utilities and pavement construction.

Posted by: Network Improvements Team on 11 August 2021 09:16

Last week, progress was made laying the kerbs and edgings that form the carriageway and new footpath. Because the majority of utility works have now been completed, there are no obstacles to laying the kerbs and edges, which form the extents of the carriageway. Once laid, pavement construction can continue. The first pavement to be constructed will be the footpath, once the edgings have been laid at the back of the footpath. Then the lower layers will be put down before the tarmac layers. 

Week 44 edging

The main kerb line for the new carriageway has also started to be laid. 

Week 44 kerbing

Activities on site next week:

  • Finalising traffic light infrastructure, continue laying kerbs and pavement construction. 