End of week 36

Southbound verge kerb line progress

Posted by: Network Improvements Team on 14 June 2021 14:30

Last week more progress was made preparing the verge ready for the road widening. More vacuum excavation was completed, exposing  larger sections of the existing utilities. 

Week 36 Vacuum

With the space now available for the road widening, the utilities will be able to moved to their new location over the coming few weeks. 

Week 36 Verge clearance

In addition to the continued excavation work, a start was made on the new kerb line that will form the edge of the new carriageway.

Week 36 Kerbing

Activities on site next week:

  • Preparation for utilities to be moved
  • Prepare new kerb line and drainage works