Search results

End of week 44

Posted by: Network Improvements Team Posted on: 11 August 2021 09:16
Categories: August 2021

Continued progress with utilities and pavement construction.

End of week 43

Posted by: Network Improvements Team Posted on: 03 August 2021 11:08
Categories: August 2021

Continued progress with utilities and pavement construction.

End of week 42

Posted by: Network Improvements Team Posted on: 27 July 2021 09:54
Categories: July 2021

Continued progress with utilities and pavement construction.

End of week 41

Posted by: Network Improvements Team Posted on: 19 July 2021 10:52
Categories: July 2021

Continued progress with utilities and pavement construction.

End of week 40

Posted by: Network Improvements Team Posted on: 12 July 2021 09:46
Categories: July 2021

Continued progress with utilities and pavement construction.

End of week 39

Posted by: Network Improvements Team Posted on: 05 July 2021 10:35
Categories: July 2021

There is no summary for this End of week 39 blog article

End of week 37 and 38

Posted by: Network Improvements Team Posted on: 30 June 2021 10:12
Categories: July 2021

Utilities have been moved over the previous two weeks.

End of week 33

Posted by: Network Improvements Team Posted on: 24 May 2021 09:57
Categories: May 2021

Southbound verge works continue with drainage and excavations.

End of week 32

Posted by: Network Improvements Team Posted on: 18 May 2021 10:13
Categories: May 2021

Lane closure has been moved to the southbound carriageway.

End of week 31

Posted by: Network Improvements Team Posted on: 10 May 2021 10:45
Categories: May 2021

Laying of binder course in widened carriageway.